Post by : Rohit Dhiman
Track replacement work on the Kelana Jaya LRT Line will begin on Sunday, September 13, 2026, with the project scheduled to continue in phases until September 2027. The work is expected to temporarily affect selected stations on several Sunday mornings. Rapid KL said the track replacement programme will be carried out in seven phases, with different sections of the line affected during each phase. The work is being planned in stages because some sections, particularly those with longer curved alignments, require additional time to complete. During the affected periods, passengers using selected stations may experience temporary changes to normal train services. Rapid KL said stations that are not included in the affected clusters will continue operating according to their regular schedules.
The first phase will take place on September 13, 20 and 27, 2026, and will affect Taman Melati and Gombak stations.
The second phase is scheduled for November 15, 22 and 29, 2026, involving Universiti, Kerinchi and Abdullah Hukum.
The third phase will take place on January 10, 17 and 24, 2027, affecting Dato’ Keramat, Jelatek and Setiawangsa.
Further work is planned for March 14, 21 and 28, 2027, again affecting Universiti, Kerinchi and Abdullah Hukum.
The fifth phase, scheduled for May 9, 16 and 23, 2027, will affect several stations in the central Kuala Lumpur area, including Masjid Jamek, Dang Wangi, Kampung Baru, KLCC and Ampang Park. Work will continue on July 11, 18 and 25, 2027, affecting Taman Jaya, Universiti, Kerinchi and Abdullah Hukum.
The final phase is scheduled for September 12, 19 and 26, 2027, when work will return to Taman Melati and Gombak.
Read Also: Zverev Beats Darderi and the Clock to Reach US Open Quarters
To reduce inconvenience during the disruption, Rapid KL said free shuttle bus services will operate between affected stations throughout the relevant work periods. Station staff, auxiliary police personnel and Prasarana Troopers will also be deployed to help passengers understand the temporary arrangements and find alternative connections. Passengers travelling on affected Sunday mornings are therefore advised to allow extra time for their journeys and follow directions provided at the stations.
Rapid KL said ticketing machines at affected stations will be temporarily closed until 9.30am during the scheduled disruption. Passengers who need to purchase tickets will be able to use station counters instead. Holders of Rapid KL products and Touch ‘n Go can continue their journeys as usual, subject to the temporary service arrangements.
The planned works are part of efforts to replace sections of ageing track infrastructure and support the continued reliability and safety of the LRT service. According to Rapid KL, sections with longer curved alignments need more time to replace. Because of the complexity of this work, some activities may continue into the following morning. Authorities are encouraging commuters to check the latest service information before travelling, particularly if their journey involves one of the affected stations.
Commuters using the Kelana Jaya Line should check the latest announcements from Rapid KL before travelling on the affected Sunday mornings. Passengers can also seek assistance from station personnel if they are unsure about shuttle bus connections or temporary travel arrangements. The operator has advised passengers to use its official website and social media channels for updated information about the Kelana Jaya LRT works, station disruptions and alternative travel arrangements.
South Africa Paceman Anrich Nortje Ruled Out of Third Test
Anrich Nortje misses the third Test against Australia with a groin injury as South Africa prepare fo
Mumbai Indians Appoint Kieron Pollard as Head Coach for 2027 IPL
Mumbai Indians appoint Kieron Pollard as head coach for IPL 2027, replacing Mahela Jayawardene as th
Marquez Takes Australian MotoGP Pole After Early Qualifying Crash
Marc Marquez claims pole at the wet Australian MotoGP after a crash, with Alex Marquez second and Jo
MotoGP Qatar GP to Proceed Despite Regional Tensions and Safety Fears
MotoGP Qatar GP is scheduled for November 6-8 despite regional tensions, as Alex Marquez questions s
Fiji Appeals to Mark Nawaqanitawase’s Pride Ahead of Rugby World Cup
Fiji hopes Mark Nawaqanitawase will choose his ancestral homeland over Australia as the 2027 Rugby W
OpenAI and Poland’s NASK Team Up to Improve AI Safety
OpenAI and Poland’s NASK will research AI safety, security risks and stronger safeguards as concerns